{{Note|This technology has been developed in the FIThydro project! See [[Innovative technologies from FIThydro]] for a complete list.|reminder}} | {{Note|This technology has been developed in the FIThydro project! See [[Innovative technologies from FIThydro]] for a complete list.|reminder}} | ||
| − | [[Innovative::developed in FIThydro| | + | [[Innovative::developed in FIThydro|:developed in FIThydro]] |
=Introduction= | =Introduction= | ||
Revision as of 15:32, 6 July 2020
This technology has been developed in the FIThydro project! See Innovative technologies from FIThydro for a complete list.
- developed in FIThydro
Contents
Introduction
Methods, tools, and devices
During planning
During implementation
During operation
Relevant MTDs and test cases
| Relevant MTDs | |
|---|---|
| N/A | |
| Relevant test cases | Applied in test case? |
| Bannwil test case | - |
| Schiffmühle test case | - |
Classification table
| Classification | Selection |
|---|---|
| Fish species for the measure | All |
| Does the measure require loss of power production | Operational (requires flow release outside turbine) |
| - | |
| - | |
| Recurrence of maintenance | Yearly |
| Which life-stage of fish is measure aimed at | - |
| - | |
| - | |
| Movements of migration of fish | |
| Which physical parameter is addressed | N/A |
| - | |
| - | |
| - | |
| - | |
| - | |
| - | |
| - | |
| Hydropower type the measure is suitable for | Plant in dam |
| Plant with bypass section | |
| Dam height (m) the measure is suitable for | Up to 20 |
| Section in the regulated system measure is designed for | In dam/power plant |
| - | |
| - | |
| - | |
| River type implemented | Steep gradient (up to 0.4 %) |
| Fairly steep with rocks, boulders (from 0.4 to 0.05 %) | |
| Slow flowing, lowland, sandy (less than 0.05 %) | |
| Level of certainty in effect | Very uncertain |
| Technology readiness level | TRL 9: actual system proven in operational environment |
| Cost of solution | See cost table |